Week of June 6th:
REC and Tech HVAC replacement
Scheduled to have Pipe Fitters onsite at 6:00 a.m. Monday – Friday.
Planned activities:
Continue installing hangers and pipe on the Tech Building including classroom penetrations. If Tech Building is completed will move to the Rec Building.
We are not planning on shutting down the chilled water for either building this week but looking at Week of June 13th to shut down Tech building, excluding skin care.
Interior Lighting Project:
Day shift crew will be in the Fine Arts building classrooms, there will be NO swing shift crew, the day crew will be double in size.