Rec/Tech Fan coil replacement project
Week of May 30th:
Scheduled to have Pipe Fitters onsite at 6:00 a.m. Tuesday – Friday.
Planned activities:
Continue installing hangers and pipe on the Tech Building including classroom penetrations. Will start where the pipe is stubbed out at Skin Care, start the second pipe run on the first floor and proceed with the second floor.
Interior Lighting Project
Week of May 30th
Humanities 2nd and 3rd floor Day shift work
Automotive technology Swing shift work