The HVAC fan coil replacement project will begin Monday the 16 in the Technology building, they will start exterior piping work and attempt to complete as much piping in Technology 112 A, B, C as possible next week. Then they will be stopping work until after the 26th.
Prop 39:
The interior lighting upgrade to LED will begin Monday the 23rd and they will be having two crews, days and swing shift, they will be starting in Maintenance during the day and Technology after hours and continuing until complete, projected to be the end of June, we will have a detailed schedule next week.