Construction Update July 10 – M&O:

Football Field is ongoing, they continue to bring in base, which is large trucks dumping rock on field.

Locker room project is scheduled for July 27th start date, there will be preliminary core drilling on the roof for the piping, no specific date yet for that work.

Roof top units at Fine Arts and Admin, tentatively slated for the week of Aug 10th, waiting on confirmation, helicopter work would commence on Aug 11th

Electric Vehicle Charging Station project scheduled to start on July 13th, initial phase will be saw cutting and trenching for electrical and concrete pads. Location is staff stalls in North Golden West by the central plant.

Bookstore remodel scheduled to start July 14th with a completion date of July 22nd, they have a flooring delivery coming this morning.

Kaplan, no new updates.

 

*We continue to experience lighting and HVAC issues related to the power outage on Tuesday, please report any issues you may be having.