March 2016 Employee of the Month Greg Lopez, Instructional Associate, Disabled Student Programs & Services (DSPS) Greg is a huge asset to our team. He is always going above and beyond to help students and faculty with questions regarding the adaptive technology and testing accommodations. Greg has brought a tremendous amount of energy and new technology […]
Leilani French – February Employee of the Month
February 2016 Employee of the Month Leilani French, Nursing Program Assistant, School of Nursing Lani is the heart of the Nursing Program. We would be lost and would fall apart without her. She goes above and beyond every day for our faculty, staff and students. Lani has worked at GWC for many years and put […]
Construction Update 2-5-16
Measure M Construction Update: Public Safety/Community Education/Main Entry Project: Ongoing punchlist items on the interior of the building. Remaining sitework and landscape items being completed. Pedestrians/Drivers need to be cautious of ongoing deliveries. Student Services Project: On Monday, 2/8/16, the east end of the concrete overhang in front of the Bookstore entrance will be trimmed. […]
Dale Slagle Employee of the Month
December 2015 Employee of the Month Dale Slagle, Offset Press Operator III, College Support Services “Dale always goes above and beyond anything we ask for. It’s not only one time, but several times I’ve experienced how dedicated Dale is to serving everyone with an amazing attitude!”
Measure M Construction Update: 12-14-15
Public Safety/Community Education/Main Entry Project: Interior work ongoing. Window installation started this week. Site underground utility work ongoing. Periodic road closures may occur due to deliveries and work adjacent to the road. Tomorrow, 12/15, the road at the west side of the new building will be closed. Pedestrians and Drivers need to follow closure signs […]
Construction Update – 12-4-15
Measure M Construction Update: Public Safety/Community Education/Main Entry Project: Roofing work finishing up. Insulation and drywall work ongoing. Site underground utility work ongoing. Periodic road closures may occur due to deliveries. Pedestrians and Drivers need to follow closure signs and be cautious as they travel around the construction site. Main entry sign work to occur periodically. […]
11/25/15 Measure M Construction Update:
Public Safety/Community Education/Main Entry Project: Roofing work ongoing. Drywall work starts next week. Site underground utility work ongoing. Periodic road closures may occur due to deliveries. Pedestrians and Drivers need to follow closure signs and be cautious as they travel around the construction site. Main entry sign work to continue next week. Periodic closures may occur […]
Juan Barrera – November Employee of the Month
Juan Barrera, is GWC’s November Employee of the Month. The person who nominated Juan said this … Juan is one of the kindest, hardest working individuals I’ve had the pleasure to work with these many years. When he works in our area in the northwest corner of the campus, he tends to our green spaces […]
Measure M Construction Update – 11/19/15
Kaplan/ Criminal Justice Projects: The berms just east of the Theatre as well as east and south of the Community Center/Admin will be removed for the work at the Kaplan and Criminal Justice projects in the future. This includes removal of all trees and shrubs that are on the berms. This work has started today […]