Interior Lighting Project First shift only, replacement of lights in Technology building HVAC replacement project: Removal of units 1st floor of technology Continued installation of piping on Rec Ed building, they will also be laying out the pipe on the roof, no penetrations at this time. FYI – Gothard street work will begin […]
Campus Work – Week of June 13
HVAC project Rec and tech buildings Scheduled to have Pipe Fitters onsite at 6:00 a.m. Monday – Friday. Planned activities: Monday – shut down chilled water to entire Tech Building. Verify that isolation valves are working correctly. Install additional isolation valves if needed. Turn chilled water back on for Skin Care classes. Tuesday – Tech Building […]
ADA inspection company – follow up site visit
Our ADA inspection company wants to return this Wednesday to continue their assessment of the campus…. Here is the follow up buildings / areas they want to look at: bldg 6 bldg 20 bldg 5 bldg 3 bldg 4 bldg 1 bldg 19 bldg 17 bldg 26 bldg 33 bldg 36 campus exterior walkways any […]
Scheduled Work – Week of June 6
Week of June 6th: REC and Tech HVAC replacement Scheduled to have Pipe Fitters onsite at 6:00 a.m. Monday – Friday. Planned activities: Continue installing hangers and pipe on the Tech Building including classroom penetrations. If Tech Building is completed will move to the Rec Building. We are not planning on shutting down the chilled […]
Scheduled Work 5-27-16
Rec/Tech Fan coil replacement project Week of May 30th: Scheduled to have Pipe Fitters onsite at 6:00 a.m. Tuesday – Friday. Planned activities: Continue installing hangers and pipe on the Tech Building including classroom penetrations. Will start where the pipe is stubbed out at Skin Care, start the second pipe run on the first floor […]
Construction Update 5-27-16
Measure M Construction Update: Student Services Project: Building plans have been approved by DSA. The project bid earlier this week. After Board approval in June we expect to start new building construction by early July. Criminal Justice Project: Building plans went to DSA for review and approval on 5/19. We anticipate some early utility […]
Deferred Maintenance Work
The HVAC fan coil replacement project will begin Monday the 16 in the Technology building, they will start exterior piping work and attempt to complete as much piping in Technology 112 A, B, C as possible next week. Then they will be stopping work until after the 26th.
Meredith Carr – May Employee of the Month
May 2016 Employee of the Month Meredith Carr, Staff Aide, Admissions and Records Enrollment Services Meredith is ALWAYS willing to assist not only students but staff without any hesitation. Besides going above and beyond these last couple months she is awesome to work with as she always has good positive attitude and LOVES working at GWC.
Measure M Construction Update: 5-6-16
Measure M Construction Update: Student Services Project: Building plans have been approved by DSA. The bid packages are out for bid later this month. After Board approval in June we expect to start new construction by early July. Criminal Justice Project: Building plans will go into DSA for review and approval on 5/19. We […]
Pete Tafoya – April Employee of the Month
April 2016 Employee of the Month Pete Tafoya, Groundskeeper 3, Maintenance & Operations Pete has a great personnel. He always come in early and make sure the campus is cleaned before students come in. Pete has always gone out of his way to help other people on campus even when it is not his job […]