Measure M Construction Update 9/28/15

Public Safety/Community Education/Main Entry Project: Steel work ongoing at the building site. Drive lanes will be shutdown in front of the building site Tuesday 9/29 from 6am – Noon. Pedestrians and Drivers need to follow closure signs and be cautious as they travel around the construction site. Landscaping work ongoing at the main entrance. Main Entrance and Exit, access in front of the LRC and adjacent new handicap and regular parking stalls to be closed Friday and Saturday for final slurry coat and striping. City ramp/sidewalk work will occur starting next week. 

Campus Fiber Cabling/ New MDF Room Project: Final fire alarm testing scheduled for Friday 10/2 from 6am-7:45am. 

Student Services Project:  The trenching and piping work will start in a couple of weeks which runs from the east side of the Student Center load center due east to the south east corner of Cosmetology. Pedestrians need to follow closure signs and flagmen when construction traffic begins around that area.