Construction Update May 14, 2015

Public Safety/Community Education/Main Entry Project:  Grading and trenching activities ongoing this week at the building site.  There will be large trucks entering and leaving the jobsite next week to export excess soil from the site.  The adjacent sidewalk will be periodically closed throughout the week for safety reasons.  Noise level expected to be moderate to high with heavy equipment onsite. Pedestrians/Drivers need to be cautious at corner of site due to lack of visibility with construction fencing.  Main entry construction fencing will go up 5/29. 

Boys and Girls Club:  Ongoing concrete truck, material deliveries and soils export.  Noise level expected to be moderate with multiple daily deliveries.  Pedestrians/Drivers need to be aware of traffic entering and leaving the jobsite.